US 93 reconstruction through
Arlee causing concern
By
B.L. Azure

Nearly 100 Jocko Valley residents and Arlee business owners questioned
Montana Department of Transportation officials and Schillenger
Construction representatives about the Arlee couplet. (B.L. Azure photo)
ARLEE — The town of Arlee will be feeling the
brunt of the U.S.
Highway 93 reconstruction project this spring and summer as
construction crews work on the portion known as the Arlee couplet and
that has raised the hackles of folks in the area.
Close to 100 area residents attended a public
meeting last
Tuesday in the Arlee Community Center in hopes of getting a little
hackles adjustment from representatives from the Montana Department of
Transportation’s Missoula District and Schellinger Construction, the
prime contractor of the Arlee couplet section of the U.S. 93
reconstruction project.
The public meeting was called to inform
the locals on what to expect from the two sections of Highway 93 that
are being reconstructed this spring and summer.
The Evaro to
McClure Road project begins at U.S. Highway 93 milepost 6.4 atop Evaro
Hill and extends north through Evaro onto the Flathead Indian
Reservation ending at U.S. 93 milepost 12.8.
The McClure Road to North of Arlee Couplet project
begins at
the U.S. 93 milepost 12.75 and extends north through Arlee ending at
milepost 18.5.

Arlee area residents and business owners query Montana Department of
Transportation officials about a myriad of concerns related to the
Highway 93 reconstruction project at last week's public information
meeting. (B.L. Azure photo)
It was the latter project, especially the in-town
disruption
caused by construction of the couplet that was caused the most concern
among the public. Noise, speed limits, safety concerns about school
children, business access, sight pollution, lost parking spaces and
dust abatement were the main concerns exhorted.
However, more
questions than answers came out of the meeting. But the parties
involved promised to get the answers and to work closely with concerned
citizens and entities to alleviate, as much as possible, the disruption
caused by the major construction project.
The Arlee couplet is comprised of, among other
things, the
southbound and northbound lanes of U.S. 93. The existing roadway
through town will be reconstructed as a two-lane northbound roadway. A
new two-lane southbound lane has been constructed just west of town
approximately two blocks west of the existing highway through town.
The
business community is concerned about public access to their businesses
during the construction window, which ends Oct. 1, as per the contract.
Nathan Malmin, U.S. 93 reconstruction
superintendent for
Schellinger Construction, said the southbound lane would be paved by
the end of this week. If the schedule holds the two-way traffic on the
present highway will then be shifted to the new southbound lane Monday,
April 27. Work will then begin on the new northbound lanes through
town. The new southbound lane will temporarily be a two-way highway
until the northbound lane is finished.
They will also be paving four east-west streets -
North
Couture, Finley Creek, Wessinger and Whitworth - that link the
northbound and southbound sections of the couplet. All the in-town
highway and street reconstruction sections will be paved with curb and
gutters as well as other amenities.
Malmin told those in attendance that there would
be accesses to
the Arlee businesses from the new roadway on the west side of town. “We
will do our best to maintain smooth access to the businesses from the
southbound lane,” he said, adding that he understood the concerns but
work is proceeding according to contract as well as the warm weather
needed to properly lay asphalt. “This is construction season and we
want to finish this (before cold weather arrives).”
Ed Toavs, MDT Missoula District engineer said
there would be
signage on the new southbound lane that directs motorists to the Arlee
businesses.
“There will be four accesses along with signs to
let people
know you are open for business,” Toavs said. “There will not be small
signs for individual businesses but large ones with businesses listed.
Signs seem to work well.”
 Surveyors
do site work along North Couture Loop Road in Arlee where gutters and
asphalt will be poured and laid. (B.L. Azure photo) Some owners of property adjacent or
close to the new southbound lane that skirts the west side of town
expressed dissatisfaction with how close their homes and property are
to the new highway. Dust, noise, lighting, vibration, parking loss and
fencing along the new southbound lane topped their concerns.
Those who expressed concerns said they were
promised abatement of the problems during public meetings years ago.
“We’re construction, we aren’t involved in the
design. We come
in with the designs and do the work,” said John Benda, MDT Missoula
District construction engineer in charge of the reconstruction project.
“I don’t know what you were told back then. Some times we can do
something about concerns but we are here to build the highway.”
Benda said MDT would review the concerns expressed
and to see
how much they can deviate from contract language to abate the perceived
problems. However, he added that the contract had been let and there
couldn’t be any large deviations from contract language and
requirements. He said the concerns about the unattractiveness of the
proposed chain link fence along the southbound lane were addressable.
He acknowledged that a byproduct of the project would be loss of on
street parking as well as loss of parking lot spaces at the Arlee
Senior Citizens Center.
Concern was also expressed about the safety of
school children
who have to cross Highway 93 to get to school and who will be exposed
to the project once school is out.
US 93
reconstruction project
ARLEE — U.S. Highway 93 reconstruction work is
progressing on two sections: the Evaro to McClure Road section, and the
McClure Road to north of Arlee couplet section. Motorists on Highway
should be aware of the reduced speed limits, temporary stoplights,
construction equipment entering and exiting the highway, flaggers and
other construction-related employees.
Work in the areas began March 9 and crews for the
time being will work the traditional five-day workweek from 7 a.m. - 5
p.m. There will be no work done from July 2-7. The work is to be
completed by Oct. 1, 2009.
• The Evaro to McClure Road project begins at U.S.
Highway 93 milepost 6.4 atop Evaro Hill and extends north through Evaro
onto the Flathead Indian Reservation ending at U.S. 93 milepost 12.8.
The project consists of re-construction resulting
in the extension of about 1.4 miles of the four-lane undivided roadway,
two-lane roadway with turn lanes, and alternating passing lanes for
north and southbound traffic.
There will also be the relocation of approximately
one mile of MRL Railroad line in Evaro. Ten wildlife crossing
structures, a new bridge over the MRL Railroad tracks near the Grey
Wolf Peak Casino, formally Joe’s Smoke Ring and one wildlife
over-crossing will be built.
A box culvert will be installed at the north end
of the project, traffic control will be in place and the public can
expect reduced speed and short delays.
The public is advised to watch for trucks entering
the roadway on the south end of the project at Evaro; expect reduced
speeds and short delays.
• The McClure Road to North of Arlee Couplet
project begins at the U.S. 93 milepost 12.75 and extends north through
Arlee ending at milepost 18.5.
The section project will consist of
re-construction resulting in two-lane roadway with alternating passing
lanes for north and southbound traffic.
Construction of a divided four lane roadway and
couplet in Arlee as well as streetscape improvements increasing
pedestrian safety and use will be installed in Arlee.
Reconstruction is underway, expect reduced speed
limits 35 mph and minimal delays.
Once the two sections are completed U.S. Highway
93 will be reconstructed from Evaro to Red Horn Road, near the 44 bar
and from north of Ronan near Spring Creek to the junction of U.S. 93
and Montana 35 near Polson.
The north of Ronan to Red Horn Road is the sole
remaining section of the project that remains to be completed.
For more information, contact John Benda, Montana
Department of Transportation Missoula District construction engineer at
726-3005.
Ed Toavs, MDT Missoula District engineer, said the
highway
department would meet with school administrators to coordinate the
effort to provide safe crossings with a flag person at specific points
along the in-town route so children would not be crossing everywhere
along the route. The contract calls for amber flashing lights at
highway crossing points.
Another huge concern was the annual doings related
to the
Fourth of July and the effect of an under construction northbound lane
occurring in the present U.S. 93 footprint will have on logistics.
Construction work will be shut down from July 2-7, as required by the
contract.
Jim Malatare, Arlee District representative on
Confederated
Salish and Kootenai Tribal Council said planning access for the annual
Arlee Celebration has to begin immediately.
“We will get together with the powwow committee
and find out
what’s doable,” Benda said, adding that dust abatement efforts would be
95 percent effective. “These kind of problems can be worked out.”
Benda said the lion’s share of the reconstruction
work on the
Arlee couplet should be completed by the end of August or first part of
September.
“We are hopeful that we can have this done as
early as the end
of July but probably it will be done no later than the first of
September,” Benda said, adding that the other reconstruction work such
as landscaping, lighting and other amenities should be completed by
Oct. 1. They will also try to chip seal the highway lanes and side
streets by then, weather permitting.
“We’ve come to build the real deal on a time
schedule,” Benda
said. “Any problems that have been left unresolved, we have to resolve
them. We are used to that and we do that.”
All the construction representatives said they
appreciate the
patience and understanding of the public. And although it may seem like
an eternity to some the finished project would be well worth the wait.
|