There is a light at the end
of the U.S. 93 construction tunnel and it is green
By
B.L. Azure

The long lines and slow moving traffic related to the U.S. Highway 93
reconstruction through Pablo should be over by this fall if all goes
well. (B.L. Azure photo)
PABLO - The end is near - relatively speaking -
for the Spring
Creek to Minesinger Trail section of the U.S. Highway 93 reconstruction
project on the Flathead Indian Reservation, according to those in the
know.
Last Wednesday evening representatives from the
Montana
Department of Transportation and Riverside Construction gave a baker's
dozen or so folks the latest information on the progress of the nearly
seven mile section of the divided four-lane highway reconstruction.
The
Spring Creek to Minesinger Trail section which has been under
construction for nearly two years will be a divided four-lane with a
separated bicycle-pedestrian path along the entire route. There will be
streetscape improvements in Pablo that promotes bicycle and pedestrian
use. There will be five wildlife-crossing structures as well as the Mud
Creek overpass structures.
Jim Mitchell, MDOT, acknowledged the
inherent traffic-flow problems related to the project and said that the
public would have blacktop to travel on throughout construction.

Tribal employees Larry Hall and Jason Adams discuss the access closures
with representatives from the Montana Department of Transportation and
Riverside Construction at last Wednesday's Highway 93 public
information meeting. (B.L. Azure photo)
Mitchell said property- and business-owners would
have access
to their property. However, when queried about access problems to the
Salish Kootenai Housing Authority complex by SKHA Director Jason Adams,
Mitchell said that they do happen but promised to do a better job
communicating temporary access closures with affected parties and the
public. There are message boards within the construction area that
advise motorists on the closures. He told Adams that the SKHA area
would have access from now on.
One access that will be
eliminated is the junction of old U.S. 93 with U.S. 93 in north Pablo
near the Plum Creek Mill. Access to the north Pablo area will be at
Light Road.
Paving will begin on the southbound lanes of the
four-lane
highway the first part of April. By mid-July paving will begin on the
northbound lanes.
"That will basically complete the job for the
road," Mitchell
said, adding that work of related amenities will continue into the
fall. Some of the amenities include bicycle and pedestrian paths,
landscaping, fencing, wildlife crossings and potentially a pedestrian
overpass near Salish Kootenai College and the tribal complex. "The
project should be completed this fall."
The new highway will have undulating curving
features like the
completed sections near Arlee and St. Ignatius. People can get a bird's
eye view of the St. Ignatius area section from the top of Post Creek
Hill.
There will be four traffic-signal lights in
Pablo-area as part
of the project. They will be located at U.S. 93's junctions: at the new
Division Street: at Pablo West-Clairmont Road; at Light Road-Courville
Trail; and at Minesinger-North Reservoir Road.

Mission Valley Power line crews reroute the existing power lines
through Arlee as part of the U.S. 93 Highway reconstruction project.
(B.L. Azure photo)
In the southern part of reservation the plans for
the two
sections of the reconstruction project have been finalized but there
are a couple of right-of-way issues that have to be hammered out with
property owners. Those right-of-ways presently in negotiation are
located in the McClure Road to the north end of Arlee section. The
Evaro to McClure Road section right-of-way issues are settled and
construction is slated to begin this summer around July. If the
right-of-way issues are settled soon in the McClure Road to north Arlee
construction could begin there near the end of July.
Mission Valley Power crews are currently moving
power lines in the Arlee area as part of the project.
The McClure Road to the north end of Arlee section
will be
primarily a two-lane highway with alternating passing lanes. There will
be some sections of divided four-lane where the roadway morphs into the
divided couplet routes through Arlee. There will streetscape
improvements with bicycle and pedestrian routes.
The Evaro to
McClure Road section will have about 1.4 miles of undivided four-lane
starting at the top of Evaro Hill. About a mile of Montana Rail Link
track will have to be relocated to make room for the four-lane road.
Then it will be primarily a two-lane highway with alternating passing
lanes and turn lanes. There will be 10 wildlife crossings structures as
well as a new bridge over MRL tracks near Grey Wolf Casino (formally
Joe's Smoke Ring) and one wildlife over pass structure.
The final special Environmental Impact Statement
for the Red
Horn Road to Spring Creek Road is near completion. A record of decision
on the preferred alternative should be made sometime this summer. Once
that is done the project goes to the design phase, then bidding and
finally construction.
The entire 56.3-mile project that stretches from
the top of
Evaro Hill to the U.S. 93-Montana 35 junction in Polson is scheduled
for completion in 2009. But when it comes to construction projects
there are always extenuating circumstances that put a hitch in the
giddy-up and extend the best-laid plans of people.
"This job, when we're finished is going to change
the
landscape," Mitchell said. "It will be a lot safer road with less
congestion and it will be very nice visually."
|